Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to weather conditions and existing conditions     found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible. 

What to Expect for the Week of May 6th to May 10th, 2024

• West Elevation Activities: Metal panel and ACM installation. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate.

• North Alley (Albany St. side) Activities: Regrading and back filling utilities at the fire pump house. 

• East Utility Yard Activities: Rebar, form and pour at the utility pads and separation walls.  

• East Elevation: Installation of Z-girt, metal panels, window install and sloped glazing. 

• South Elevation / Plaza: Framing, sheathing, waterproofing, installation of Z Girt, insulation, and metal panels. Granite installation, plaza concrete, steel install and demolition, steel replacement, loading dumpsters and receiving deliveries at the East Newton Street gate.

What to Expect for the Week of May 13th to May 17th, 2024 

• West Elevation Activities: Continue with Metal panel installation. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate as well as receiving deliveries.

• North Alley (Albany St. side) Activities: Water line underground utility work, form, and place slab at the end of the fire pump house.

• East Utility Yard Activities: Continue with forming, prep and pour slabs/ separation walls. 

• East Elevation: Z Girt insulation and metal panel install along with window and sloped glazing install. 

• South Elevation/Plaza: Framing, sheathing, waterproofing, Z-Girt, insulation, and Metal Panel installation.  concrete placement, steel demolition/ replacement. Setting structural steel at the activity terrace roof. Dumpsters and deliveries will be handled through the East Newton Street gate. We are expecting to have a crane on site to remove the remaining sections of mast climbers from the South side along East Newton St. and start relocating them to the plaza/ terrace roof.  

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice