Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise and we are working on trying to minimize the disturbance as much as possible.
What to Expect for the week of June 5th, to June 9th, 2023
• North Elevation Activities include metal panel installation, framing, curtainwall installation and dismantling mast climbers. A crane truck will access the North Alley way this week to dismantle the mast climbers – this will temporarily limit access to the east end of the Alley. A spotter will be on the ground to help coordinate access for the residents as needed.
• CMU veneer installation will continue along the West and South elevations. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate.
• We will continue with Plaza structural concrete and steel demolition, loading dumpsters and receiving deliveries at the East Newton Street gate.
• West Elevation Activities: Mast climber installation, framing, AVB installation, curtain wall demolition and curtain wall installation.
What to Expect for the week of June 12th to June 16th, 2023
• North Elevation Activities include metal panel installation, framing, curtainwall installation and dismantling mast climbers. A crane truck will access the North Alley way this week to dismantle the mast climbers – this will temporarily limit access to the east end of the Alley. A spotter will be on the ground to help coordinate access for the residents as needed.
• CMU veneer installation will continue along the West and South elevations. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate.
• We are expecting to continue with soil removal and utility installation at the East Utility Yard near the BU Dental building.
• West Elevation Activities: Mast climber installation, framing, AVB installation, curtain wall demolition and curtain wall installation are expecting to be ongoing. We expect to start installing metal panels as well.
• At the east end of the North Alley, utilities work and material load out will continue.
• Northeast utility work will commence this week, working out into Albany Street.
Click here for Two Week Look Ahead Flyer