Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters intermittently throughout the duration of the project mainly from the East side of the site along Albany Street.
What to Expect for the week of January 23rd to January 27th, 2023
• North Alley utility work will be ongoing through the coming weeks.
• Load-out to continue along the West and South sides of the building, accessing through the gate on East Newton St. along with access through the gate between the Preston Building and Doctor’s Office Building (DOB).
• We are expecting to continue with the utility upgrades in the “alley” adjacent to the BU dental building.
We will be finishing up the form work and rebar for the concrete placement of the curbs and corbels.
• Window demolition and framing infills will continue along the North elevation for the coming weeks.
What to Expect for the week of January 30th to February 3rd , 2023
• North Alley utility work will be ongoing through the coming weeks.
• Load-out to continue along the West and South sides of the building, accessing through the gate
on East Newton St. along with access through the gate between the Preston Building and Doctor’s Office Building (DOB).
• We are expecting to continue with the utility upgrades in the “alley” adjacent to the BU dental building.
• Window demolition and framing infills will continue along the North elevation for the coming weeks.
• We are expecting a concrete placement along the East elevation on the back side of BU Dental building this week, accessing from East Newton St. with the concrete trucks and pump.
Click here for Two Week Look Ahead Flyer