Project Photos and Updates

 

Two Week Look Ahead

Please note that this schedule may change due to weather or existing site conditions. Throughout the project, dumpsters may be swapped out and deliveries may arrive intermittently, primarily from the east side of the site along Albany Street. Some work may create noise or vibration, and the project team will continue working to minimize disruption to residents and neighbors as much as possible.

What to Expect for the Week of June 22nd to June 26th, 2026
  • West: Crews are expected to grade and backfill the underground conduit. A crane is also planned along the west side to install the security fence structure.
  • North: Crews may begin removing planter material and looking into reported leaks this week.
  • East Utility Yard: The temporary diesel fire pump will continue to be maintained and will run for about 3 minutes every 18 hours. The new fire pump is also expected to be commissioned this week.
  • East Elevation: Window testing and roof flood testing are scheduled along the east side of the building.
  • South Elevation/Plaza: Crews will continue overhead ACM punch-list work. Material deliveries are expected throughout the week. Excavation and installation of drywell structures may begin with trucks and equipment entering the East Newton Street gate.
What to Expect for the Week of June 29th to July 3rd, 2026
  • West: A crane is planned along the west side to install the security fence structure.
  • North: A crane is scheduled for Valet Lot. Resident access through the north alley will remain open, and a ground crew will be available to help maintain safe access as needed.
  • East Utility Yard: The temporary diesel fire pump will continue to be maintained and will run for about 3 minutes every 18 hours. The fire pump test is scheduled for Tuesday, June 30, at 9:00 a.m.
  • East: Crews are expected to excavate for light poles and conduit, then continue rough grading and backfilling site utilities.
  • South Elevation/Plaza: Crews will continue overhead ACM punch-list work, with material deliveries expected throughout the week. Trucks and equipment will enter through the East Newton Street gate.

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice