Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible.
What to Expect for the Week of June 9th to June 13th, 2025
• West: Concrete placement this week stated just South of the Sally port trucks entering through the East Newton St. gate.
• North: No activity was planned for this area.
• East Utility Yard: Temporary diesel fire pump will be maintained and will run for approx. 3 min. every 18hours.
• East: Roof install along with core drilling roof drains over the loading dock.
• South Elevation/Plaza: Continue with ACM panel install, Granite veneer install, coring for plaza drains and form and pour topping slab. Trucks and equipment will be entering through the East Newton St. gate.
What to Expect for the Week of June 16th to June 20th, 2025
• West: No activity planned for this area
• North: Concrete placement scheduled this week, trucks on the NE corner of the site.
• East Utility Yard: Temporary diesel fire pump will be maintained and run for 3 min. approximately every 18 hours.
• East: Roof install along with core drilling roof drains over the loading dock.
• South Elevation/Plaza: Continue with ACM panel install, Granite veneer install, coring for plaza drains and form and pour topping slab. Trucks and equipment will be entering through the East Newton St. gate.
Click here for Two Week Look Ahead Flyer