Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to weather conditions and existing conditions     found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible. 

Winter cleanup: Snow removal/plowing, and ice melt applications around the perimeter of the site will be performed as needed throughout the winter months. 

What to Expect for the Week of February 10th to February 14th, 2025 

• West Elevation: No activities planned for this area.

• North Elevation: No activities planned for this area. 

• East Utility Yard: No activities planned for this area.  

• East Elevation: No activities planned for this area.  

• South Elevation/Plaza: Steel install, framing, sheathing, waterproofing, installation of Z Girt, insulation, curtain wall and metal panel installation. Granite veneer install will continue along with concrete placement. Daily fuel delivery.

What to Expect for the Week of February 17th to February 21st, 2025

• West Elevation: No activities planned for this area.  

• North Elevation: No activities planned for this area.  

• East Utility Yard: No activities planned for this area. 

• East Elevation: No activities planned for this area. 

• South Elevation/Plaza: Curtain wall install, framing, sheathing, waterproofing, Z-Girt, insulation, and metal panels. Trucks and equipment will be entering through the East Newton St. gate. Granite veneer install will continue along with concrete placement. Daily fuel delivery.

 

Saturday February 22nd, we have a crane scheduled at BMC’s Preston parking lot for the day to off load material to the roof. 

Click here for Two Week Look Ahead Flyer