Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to weather conditions and existing conditions     found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible. 

What to Expect for the Week of September 30th to October 4th, 2024

• West Elevation Activities: Finish up ACM panel install.

• North Alley (Albany St. side) Activities: Soil removal, clean up and prep for binder.

• East Utility Yard Activities: Grading and Chain link fence installation. 

• East Elevation: Punch list, mast climber dismantling

• South Elevation/Plaza: Set up mast climbers, framing, sheathing, waterproofing, installation of Z Girt, insulation, curtain wall and metal panel installation. We will have crane truck at the plaza loading the 7th floor drywall. 

 

Saturday October 5th: We will have a crane and support trucks in the BMC lot loading the building with the new transformer and removing the old. 

What to Expect for the Week of October 7th to October 11th, 2024 

• West Elevation Activities: Concrete placement on the interior of the building. Trucks will enter the site from the BMC lot and the gate at the Preston Family Building. Finish metal panel install over Sally Port.  

• North Alley Activities: We are anticipating starting the remainder of grading and asphalt binder at the North Alley (NE corner). 

• East Utility Yard Activities: Fence install and install area drains and rough grade. 

• East Elevation: No activities scheduled for this area.

• South Elevation/Plaza: Curtain wall install, framing, sheathing, waterproofing, Z-Girt, insulation, and metal panels. Steel installation and material deliveries to the 4th floor and concrete placement. 

Click here for Two Week Look Ahead Flyer