Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible. As snow events occur, we will be managing the perimeter of the site for public safety. Plowing and snow removal along the North Alley and sidewalks that surround the property will be maintained.

What to Expect for the Week of April 15th to April 19th, 2024 

• West Elevation Activities: Continue with Metal panel installation. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate as well as receiving deliveries.

• North Alley (Albany St. side) Activities: Continuing with utilities, form, and place slabs. We have a crane expected for this week depending on the weather to load material to the 4th floor. 

• North Elevation Activities: Z Girt, insulation, metal panel and ACM installation. 

• East Utility Yard Activities: Continue with utilities in and around the grade beams, back fill, prep & pour slab. 

• East Elevation: Z Girt insulation and metal panel install along with window and sloped glazing install. 

• South Elevation/Plaza: Framing, sheathing, waterproofing, Z-Girt, insulation, and Metal Panel installation.  concrete placement, steel demolition/ replacement. Setting structural steel at the activity terrace roof. Dumpsters and deliveries will be handled through the East Newton Street gate. 

What to Expect for the Week of April 22nd to April 26th, 2024

• West Elevation Activities: Metal panel and ACM installation. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate. Concrete placement will occur this week through a louver opening to the upper floors. 

• North Elevation Activities: Z Girt, insulation, and metal panel installation.

• North Alley (Albany St. side) Activities: We have (2) cranes lined up for this week on NE corner of the site to take deliveries and load the 4th floor mech floor. 

• East Utility Yard Activities: prep and slab placements. Stone and gravel deliveries will occur this week entering in from the Albany St. gate.

• East Elevation: Mast climber set up and continue with Z-girt, metal panels, window insulation and sloped glazing. 

• South Elevation / Plaza: Framing, sheathing, waterproofing, installation of Z Girt, insulation, and metal panels. Granite installation, plaza concrete, steel demolition, steel replacement, loading dumpsters and receiving deliveries at the East Newton Street gate.

Click here for Two Week Look Ahead Flyer