Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. 

What to Expect for the week of November 21st to November 25th, 2022

• We are expecting to continue with the concrete cutting and demolition work along the BU Dental “alley” this week. This work will generate elevated noise and vibration. 

• Load out of debris and material will continue along the West side, from the 2nd floor. Expect elevated noise as dumpsters are loaded. Trucks and equipment will access through the gate between the Preston and Doctor’s Office Building (DOB)

• We are expecting to start with the utility upgrades in the “alley” adjacent to the BU dental building, starting from East Newton St. and working north along the “alley”. In this same area, we are continuing the concrete, precast demo, deck removal and steel replacement.  

• We expect to continue with the utility work along the North Alley and out into Albany St. with partial lane closure and sidewalk detours. 

• We will be setting up mast climbers and starting the CMU infill on south end of the building on the SW corner along East Newton St. 

• Job site will be closed on Thursday 11/24 for Thanksgiving.

What to Expect for the week of November 28th to December 2nd, 2022

• We are expecting to continue with utility work along the North Alley and out into Albany St. with partial lane closure and sidewalk detours. 

• Continue to load-out debris and material along the West side from the 2nd floor. Expect elevated noise as we load dumpsters. Trucks and equipment will access through the gate between the Preston and Doctor’s Office Building (DOB).  

• We are expecting to continue with the utility upgrades in the “alley” adjacent to the BU dental building, starting from East Newton St. and working north along the “alley”. In this same area, we will be doing the steel replacement. 

• We are planning on finishing up the utility work along the West end of the site with the sewer and storm tie in at East Newton St. 

• We will be continuing the CMU infill on south end of the building on the SW corner along East Newton St. 

Click here for Two Week Look Ahead Flyer 

 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice