Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible. 

What to Expect for the Week of May 12th to May 16th, 2025 

• West Elevation: 5/17/25 we will be receiving several truckloads of truss wall material and will be off loading them into the second floor windows from the BMC lot and will continue to load through the windows as needed. We are also expecting a concrete placement this week staged just South of the Sally Port.

• North Elevation: We are expected to have a concrete pump truck set up in the NE corner of the site for a concrete placement through our load dock in the basement. 

• East Utility Yard: Temporary Diesel fire pump will be maintained and will run for approx. 3 min. every 18hours.  

• East Elevation: Curtain wall install and the completion of the ACM panels.  

• South Elevation/Plaza: Steel install, AVB and waterproofing, installation of Z Girt, insulation, curtain wall and metal panel installation. Trucks and equipment will be entering through the East Newton St. gate. Granite veneer install will continue along with plaza slab prep and concrete placements. Daily fuel deliveries.

What to Expect for the Week of May 5th to May 9th, 2025

• West Elevation: We are expecting deliveries, offloading Truss Wall material for H building and hoisting through the 2nd floor windows this week. We are looking to place concrete this week inside the building, trucks and pump will be staged at the South end of the Sally Port and trucks entering from East Newton St. 

• North Elevation: No activities planned for this area.  

• East Utility Yard: Temporary Diesel fire pump will be maintained and will run for 3 min. approximately every 18hours.

• East Elevation: Curtain wall install and the completion of the ACM panels.  

• South Elevation/Plaza: Steel install, AVB and waterproofing, installation of Z Girt, insulation, curtain wall and metal panel installation. Trucks and equipment will be entering through the East Newton St. gate. Granite veneer install will continue along with plaza slab prep and concrete placements. Daily fuel deliveries.

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice