Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible.
What to Expect for the Week of March 31st to April 4th, 2025
• West Elevation: Roof work and equipment install expected this week
• North Elevation: No activities planned for this area.
• East Utility Yard: Temporary Diesel fire pump is installed and will run for approx. 3 min. every 18hours or so.
• East Elevation: No activities planned for this area.
• South Elevation/Plaza: Steel install, AVB and waterproofing, installation of Z Girt, insulation, curtain wall and metal panel installation. Trucks and equipment will be entering through the East Newton St. gate.
Granite veneer install will continue along with concrete placement. Daily fuel deliveries.
• Crane scheduled for Saturday 4/5 in the BMC Preston parking lot where they will take delivery of the new elevator equipment and hoist through the roof of the H building while removing the old equipment.
What to Expect for the Week of April 7th to April 11th, 2025
• West Elevation: Roof work and equipment install expected again this week, concrete placement with pump truck along the North end of the Sally port pouring concrete in the basement of H building accessing through BMC Preston lot gate.
• North Elevation: No activities planned for this area.
• East Utility Yard: Temporary Diesel fire pump is installed and will run for 3 min. approximately every 18hours.
• East Elevation: No activities planned for this area.
• South Elevation/Plaza: Curtain wall install, AVB, Sealants and waterproofing will continue Z-Girt, insulation, and metal panels. Trucks and equipment will be entering through the East Newton St. gate. Granite veneer install will continue along with concrete placement. Daily fuel deliveries.
Click here for Two Week Look Ahead Flyer