Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to the weather conditions and existing conditions     found while performing the tasks below. We will be swapping out 30 yd. dumpsters and receiving deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibration and noise, and we are working to minimize the disturbance as much as possible. We will be managing ice melt and snow removal as needed around the perimeter of the site.

 

What to Expect for the Week of February 23rd to February 27th, 2026
  • West: No work activities scheduled for this area.
  • North: We are expecting a crane in the Valet lot weather permitting to hoist steel material onto the H and Q roof. The crane activity will not impede access by residents to their parking spaces along the North Alley during this operation.
  • East Utility Yard: Temporary diesel fire pump being maintained and running for 3 min. approximately every 18 hours. We expect to continue with the East utility yard stairs forming
  • East: No work activities scheduled for this area.
  • South Elevation/Plaza: Crew working overhead on ACM punch list this week. Several material deliveries are scheduled throughout the week. We are expecting a crane this week to be set up on the edge of the plaza and boom lifts to install building signage this week. Trucks and equipment will be entering through the East Newton St. gate.

 

What to Expect for the Week of March 2nd to March 6th, 2026
  • West: Scheduling a concrete placement with Boom pump -- trucks entering from the East Newton St.
  • North: Fire pump start up scheduled for this week. We are expecting a crane in the Valet lot to hoist steel onto the H and Q roof this week.
  • East Utility Yard: Temporary diesel fire pump being maintained and running for 3 min. approximately every 18 hours. We expect to continue with the form work/ rebar and the placement of the utility stairs.
  • East: No work activities scheduled for this week. 
  • South Elevation/Plaza: Several material deliveries are scheduled throughout the week. We are continuing with the crane set up on the edge of the plaza and boom lifts to install perforated signage. Trucks and equipment will be entering through the East Newton St. gate

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice