Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. 

What to Expect for the week of September 19th to September 23rd, 2022

• We are expecting to pour concrete this week at the Sallyport (West side) and the former H-loading dock area (Northwest corner). Concrete trucks will be entering through the gate at the Valet lot (Northwest corner).

• We are expecting to continue with concrete cutting and demolition work along the BU Dental Alley in the coming weeks. 

• Saw cutting and precast demolition along the Southeast side of the building at the front entrance at 88 East Newton St. will continue this week. Increased noise and vibration may be expected. 

• Utility excavation along the North Alley is expected to continue this week with large heavy equipment. Expect noise and vibration intermittently. 

• Loading out of debris and material will continue along the West side, from the 4th floor. Expect elevated noise as dumpsters are loaded. Trucks and equipment will access through the gate between the Preston and Doctor’s Office Building (DOB). 

• We will be rerouting small portions of the sidewalks along East Newton St. as we prepare for utility work and more exterior precast demolition. 

• We plan to relocate the jersey barriers and fence line along the East Newton St., relocating the pedestrian sidewalk and removing the parking meters/ bus stop this week or next week depending on the weather. 

What to Expect for the week of September 26th to September 30th, 2022

• Utility excavation along the North Alley will continue this week with large heavy equipment. Expect noise and vibration intermittently throughout the coming weeks for this work. 

• We anticipate continuing with concrete work at the H loading dock and will access the area down the North Alley and the Valet lot with concrete trucks and equipment. 

• Continuing this week, we will saw cut and remove concrete at the plaza deck and precast panels (Southeast) at the front entrance at 88 East Newton St. Increased noise and vibration may be expected. 

• We are expecting to continue with concrete demolition work along the alley next to BU Dental. This will generate elevated noise and vibrations throughout the coming weeks. 

• Load-out of debris and material will continue along the West side from the 4th floor. Expect elevated noise as we load dumpsters. Trucks and equipment will access through the gate between the Preston and Doctor’s Office Building (DOB).

Click here for Two Week Look Ahead Flyer 
Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice