Project Photos and Updates

 

Two Week Look Ahead

 

Please note that the schedule below may change due to weather, site conditions, or other project needs. During this work, dumpsters may be swapped out, and deliveries may arrive at different times, primarily from the east side of the site along Albany Street. Some activities may cause noise or vibration. The project team will continue to work to limit disruption to residents and neighbors whenever possible.

 

What to Expect: November 2-6, 2026
  • West/Sally Port: Crews will complete final grading in preparation for paving, which has been pushed to Monday of next week.
  • North/Alley: Crews will pressure test, video-inspect, and flush both the sewer and drain manholes. Residents still cannot access the North Alley during this work. Resident access will be temporarily closed for part of the day while work is completed, and additional resident parking will be available in the valet lot as needed. Finish paving has been pushed to a later date, pending confirmation from the paving company.
  • East/Utility Yard: Crews will continue grading, setting curbs, and placing concrete for the sidewalks.
  • South/Plaza: Material deliveries, plaza grading, concrete placement, and curb installation are planned throughout the week. Crews will also install asphalt binder on the plaza deck. Trucks and equipment will enter through the East Newton Street gate.

 

What to Expect: November 9–13, 2026
  • West/Sally Port: Crews will continue repairing the existing catch basins.
  • North/Alley: Crews will prep for finish paving and wait for final confirmation from the paving company.
  • East/Utility Yard: Crews will grade and prepare areas for curbing, sidewalk construction, and concrete placement.
  • South/Plaza: Material deliveries, plaza grading, granite curb installation, formwork, rebar installation, and concrete placement are scheduled throughout the week. Trucks and equipment will enter through the East Newton Street gate.

 

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice