Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to the weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and receiving deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibration and noise, and we are working to minimize the disturbance as much as possible

What to Expect for the Week of November 17th to November 21st, 2025:
  • West: During the week, we will be hoisting the stored material up to the 3rd floor through a loading area which will be done from on site.
  • North: No work scheduled for this area other than stored material being moved inside the building throughout the week.
  • East Utility Yard: No additional work outside of the temporary diesel fire pump being maintained and running for 3 min. approximately every 18 hours.
  • East: Continue with ACM panel install and punch list along this elevation, core drill and install terrace roof drains and piping over the loading dock.
  • South Elevation/Plaza: We are scheduling material deliveries throughout the week. We are expecting a crane set up on the edge of the plaza installing the perforated sign. Trucks and equipment will be entering through the East Newton St. gate.
What to Expect for the Week of November 24th to November 28th, 2025:
  • West: During the week, we will be hoisting the stored material up to the 3rd floor through a loading area which will be done from on site.  
  • North: We are looking to schedule excess soil removal from this area that is stockpiled. Also, stored material from the paved area will be moved inside the building as needed throughout the week.
  • East Utility Yard: No additional work outside of the temporary diesel fire pump being maintained and running for 3 min. approximately every 18 hours.
  • East: Continue with ACM panel install and punch list along this elevation, core drill and install terrace roof drains and piping over the loading dock.
  • South Elevation/Plaza: We are scheduling material deliveries throughout the week. We are expecting a crane set up on the edge of the plaza installing the perforated sign. Trucks and equipment will be entering through the East Newton St. gate.

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice