Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible. As snow events occur, we will be managing the perimeter of the site for public safety. Plowing and snow removal along the North Alley and sidewalks that surround the property will be maintained.

What to Expect for the Week of Feb. 19th to Feb. 23rd, 2024 

• West Elevation Activities: Z Girt, insulation, and metal panel installation. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate.

• North Alley (Albany St. side) Activities: Continuing with rebar install, forming and pouring grade beams. The crane scheduled for 02/20/24 had to be cancelled due to lack of parking availability. 

• North Elevation Activities: Z Girt, insulation, metal panel and ACM installation. 

• East Utility Yard Activities: Forming, rebar and pouring grade beams. 

• East Elevation:  Exterior framing, sheathing, blocking, waterproofing and window install.  

• South Elevation/Plaza: Framing, sheathing, waterproofing, Z-Girt, insulation, and Metal Panel installation. Granite installation, concrete placement, steel demolition/ replacement. Dumpsters and deliveries will be handled through the East Newton Street gate. We are expecting a crane to set steel this week, as well as concrete boom pump truck for slab placements and deliveries. 

What to Expect for the Week of Feb. 26th to March 1st, 2024

• West Elevation Activities: Metal panel and CMU installation. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate. 

• North Elevation Activities: Z Girt, insulation, and metal panel installation. 

• North Alley (Albany St. side) Activities: Form, rebar, and concrete placement of grade beams. 

• East Utility Yard Activities: Rebar installation, forming and pouring of grade beams and slab prep. 

• East Elevation: Exterior window install, sloped glazing install, framing, sheathing, blocking, AVB and window installation.

• South Elevation / Plaza: Framing, sheathing, waterproofing, installation of Z Girt, insulation, and metal panels. Granite installation, plaza concrete, steel demolition, steel replacement, loading dumpsters and receiving deliveries at the East Newton Street gate. 

Click here for Two Week Look Ahead Flyer