Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to the weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and receiving deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibration and noise, and we are working to minimize the disturbance as much as possible. We will be managing ice melt and snow removal as needed around the perimeter of the site.

What to Expect for the Week of December 1st to December 5th, 2025
  • West: Hoisting of stored material up to the 3rd floor through a loading area which will be done from on site.
  • Northeast: Shallow excavation for site conduit, grade and backfill in planter area.
  • East Utility Yard: No work scheduled for this area except for the temporary diesel fire pump being maintained and running for 3 min. approximately every 18 hours.
  • East: No work activities scheduled for this area.
  • South Elevation/Plaza: We are scheduling material deliveries throughout the week. We are expecting a crane set up on the edge of the plaza loading material to the activity terrace roof. Trucks and equipment will be entering through the East Newton St. gate.
What to Expect for the Week of December 8th to December 12th, 2025
  • West: Continuing this week, we will be hoisting stored material up to the 3rd floor through a loading area which will be done from on site.  
  • North: No work activities scheduled for this area.
  • East Utility Yard: No work scheduled for this area except for the temporary diesel fire pump being maintained and running for 3 min. approximately every 18 hours.
  • East: No work activities scheduled for this area.
  • South Elevation/Plaza: We are scheduling material deliveries throughout the week. We are expecting a crane set up on the edge of the plaza loading material to the activity terrace roof. Trucks and equipment will be entering through the East Newton St. gate

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice