Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. 

What to Expect for the week of January 23rd to January 27th, 2023

• North Alley utility work will be ongoing through the coming weeks. 

• Load-out to continue along the West and South sides of the building, accessing through the gate on East Newton St. along with access through the gate between the Preston Building and Doctor’s Office Building (DOB).

• We are expecting to continue with the utility upgrades in the “alley” adjacent to the BU dental building. 

We will be finishing up the form work and rebar for the concrete placement of the curbs and corbels.   

• Window demolition and framing infills will continue along the North elevation for the coming weeks. 

 

What to Expect for the week of January 30th to February 3rd , 2023

• North Alley utility work will be ongoing through the coming weeks.  

• Load-out to continue along the West and South sides of the building, accessing through the gate 

on East Newton St. along with access through the gate between the Preston Building and Doctor’s Office Building (DOB).

• We are expecting to continue with the utility upgrades in the “alley” adjacent to the BU dental building. 

• Window demolition and framing infills will continue along the North elevation for the coming weeks. 

• We are expecting a concrete placement along the East elevation on the back side of BU Dental building this week, accessing from East Newton St. with the concrete trucks and pump. 

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice