Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible.
Winter cleanup: Snow removal/plowing, and ice melt applications around the perimeter of the site will be performed as needed throughout the winter months.
What to Expect for the Week of March 24th to March 28th, 2025
• West Elevation: Roof work and equipment install expected this week
• North Elevation: No activities planned for this area.
• East Utility Yard: Temporary Diesel fire pump is installed and will run for 3 min. approximately every 18hours.
• East Elevation: No activities planned for this area.
• South Elevation/Plaza: Curtain wall install, AVB, Sealants and waterproofing will continue Z-Girt, insulation, and metal panels. Trucks and equipment will be entering through the East Newton St. gate. Granite veneer install will continue along with concrete placement. Daily fuel deliveries.
What to Expect for the Week of March 31st to April 4th, 2025
• West Elevation: Roof work and equipment install expected this week
• North Elevation: No activities planned for this area.
• East Utility Yard: Temporary Diesel fire pump is installed and will for approx. 3 min. every 18hours
• East Elevation: No activities planned for this area.
• South Elevation/Plaza: Steel install, AVB and waterproofing, installation of Z Girt, insulation, curtain wall and metal panel installation. Trucks and equipment will be entering through the East Newton St. gate.
Granite veneer install will continue along with concrete placement. Daily fuel deliveries.
Click here for Two Week Look Ahead Flyer