Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise that be experienced, and we are working on trying to minimize the disturbance as much as possible.
What to Expect for the week of March 13th to March 17th, 2023
• North Elevation Activities: window removal, metal panel installation, framing and curtainwall installation.
• We are expecting a concrete placement at the Plaza deck along East Newton St. this week.
What to Expect for the week of March 20th to March 24th, 2023
• North Alley utility work will be ongoing, progressing along the East side with utilities and material load out.
• We expect to continue with soil removal and utility upgrades in the East Alley adjacent to the BU Dental building.
• North Elevation Activities: window removal, metal panel installation, framing and curtainwall installation.
• We are expecting to excavate and set concrete structures along east Newton St. just inside the fence line.
Click here for Two Week Look Ahead Flyer