Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible.
What to Expect for the Week of December 2nd to December 6th ,2024
• West Elevation: No activities planning for this week.
• North Elevation: No activities planned for this week.
• East Utility Yard: Waiting on Eversource to terminate the primaries and energize the switch gear expected this week.
• East Elevation: Punch list and louver install.
• South Elevation/Plaza: Curtain wall install, framing, sheathing, waterproofing, Z-Girt, insulation, and metal panels., all trucks and equipment will be entering through the East Newton St. gate. Granite veneer install will continue along the plaza.
What to Expect for the Week of December 9th to December 13th, 2024
• West Elevation: We are planning to have concrete placements on the interior of the building. Trucks will be entering the site from the BMC lot and the gate at the Preston Family building.
• North Elevation: No activities planned for this week.
• East Utility Yard: No activities planned for this week.
• East Elevation: Complete the installation of the metal panels/ louver install.
• South Elevation/Plaza: Steel install, framing, sheathing, waterproofing, installation of Z Girt, insulation, curtain wall and metal panel installation. Granite veneer install will continue along with Concrete placement. Fuel delivery. Mast climber dismantling and relocation.
Click here for Two Week Look Ahead Flyer