Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to the weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and receiving deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibration and noise, and we are working to minimize the disturbance as much as possible.

What to Expect for the Week of November 10th to November 14th, 2025
  • West: We have Truss wall delivery scheduled for Saturday 11/15/25 with trucks entering from the BMC lot and staging there while they are offloaded and stored on site. During the week, the material will be hoisted up to the 3rd floor through a loading area which will be done from on site.   
  • North: No work scheduled for this area. 
  • East Utility Yard: We are planning to Vac excavate around the existing utilities for the new site stair foundations and complete the drainage in this area. A temporary diesel fire pump will be maintained and will run for approx. 3 min. every 18 hours. 
  • East: We are continuing with ACM panel installation and punch-listing the exterior envelope this week.
  • South Elevation/Plaza: Continue with ACM panel installation. We are scheduling material deliveries throughout the week as well as continuing to form and pour topping slabs. Demo debris removal from the areaway and loading dumpsters. Trucks and equipment will be entering through the East Newton St. gate.
What to Expect for the Week of November 17th to November 21st, 2025
  • West: During this week, we will be hoisting material up to the 3rd floor through a loading area which will be done from on site.
  • North: We are expecting the delivery and installation of the fire pump stairs and platform. Soil removal scheduled for this week.
  • East Utility Yard: We expect to start the Vac excavation for the exterior stairs at the electrical pad this week. A temporary diesel fire pump will be maintained and run for 3 min. approximately every 18 hours.
  • East: Continue with ACM panel install and punch list along this elevation, core drill and install terrace roof drains and piping over the loading dock.
  • South Elevation/Plaza: Continue with ACM panel installation. We are scheduling material deliveries throughout the week as well as continuing to form and pour topping slabs. We are expecting a crane set up on the edge of the plaza installing the perforated sign. Trucks and equipment will be entering through the East Newton St. gate.

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice