Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to weather conditions and existing conditions     found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise and we are working on trying to minimize the disturbance as much as possible. 

What to Expect for the week of Sept. 11th, to Sept. 15th,2023

• North Elevation Activities: Sloped glazing demo, exterior framing, sheathing, blocking, dismantling and relocation of the climbers. 

• We will continue with Plaza concrete, steel demolition, steel replacement, loading dumpsters and receiving deliveries at the East Newton Street gate.

• West Elevation Activities: Framing, blocking, waterproofing, curtain wall/ window installation along with Z Girt, insulation and Metal panel installation are expected to be ongoing. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate.

• East Utility Yard Activities: We will be starting the Helical piles along the BU dental building and continuing through the next couple weeks. 

• South Elevation: Continue with swing staging installation, mast climbers, framing, blocking and waterproofing. 

• North Alley (Albany side) Activities: Grading and compaction for asphalt. Installation of helical piles are scheduled this week for the fire pump pad, along with forming and pouring of the grade beams.   

What to Expect for the week of Sept. 18th, to Sept. 22nd, 2023

• North Elevation Activities: Sloped glazing demo along with exterior framing, sheathing, blocking, dismantling and relocation of mast climbers. Gilbane is working on scheduling a truck to remove the ballast material from the roof and we are expecting the noise level to be noticeable. This work will continue for several weeks. Coordination of this activity is ongoing and if the North Alley is going to be affected, Gilbane will provide notices ahead of scheduling the work activity. 

• We will continue with Plaza structural concrete, steel demolition/ replacement and concrete placements. Dumpsters and deliveries will be handled through the East Newton Street gate.

• West Elevation Activities: Framing, waterproofing, curtain wall installation, Z Girt and insulation for metal panel install.  Crews will access through the gate near the Preston Family Building and through the East Newton Street gate.

• East Utility Yard Activities: We will be continuing with the helical pile installation along the BU dental building.

• North Alley (Albany side) Activities: Continue with forming and pouring of the grade beams. excavating and installation of utilities to the new fire pump location. 

• South Elevation/Plaza: Mast climbers and swings assembly, exterior framing, blocking, and sheathing. 

Click here for Two Week Look Ahead Flyer