Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise and we are working on trying to minimize the disturbance as much as possible.
What to Expect for the week of Nov. 27th to Dec.1st, 2023
• West Elevation Activities: Framing, waterproofing, curtain wall installation, Z Girt and insulation for metal panel install. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate.
• North Alley (Albany side) Activities: Continue with installation of site utilities. Back fill and grading soil compaction, form and pour grade beams are expected to start.
• North Elevation Activities: Sloped glazing installation, exterior framing, sheathing, blocking and AVB install.
• East Utility Yard Activities: Continue with underground utilities to the equipment pads. Back fill and grading, forming, rebar and concrete placement of grade beams.
• South Elevation/Plaza: Exterior framing, blocking, sheathing and AVB ongoing.
We will continue with Plaza structural concrete, steel demolition/ replacement and concrete placements. Dumpsters and deliveries will be handled through the East Newton Street gate.
• We are expecting a crane and steel delivery on the Northeast corner of the site to set roof steel this week, it will not affect the alley.
• East Elevation: setting up swings and starting the exterior window framing, blocking and AVB.
What to Expect for the week of Dec. 4th to Dec. 8th, 2023
• West Elevation Activities: Framing, blocking, waterproofing, curtain wall/ window installation along with Z Girt, insulation and Metal panel installation are expected to be ongoing. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate.
• North Elevation Activities: Sloped glazing installation, exterior framing, sheathing, blocking and AVB install.
• North Alley (Albany side) Activities: Continue with installation of site utilities. Back fill and grading soil compaction, form and pour grade beams are expected to start.
• East Utility Yard Activities: Continue with underground utilities to the equipment pads. Back fill and grading, rebar, forming and pouring grade beams.
• South Elevation / Plaza: Continue with framing, blocking, waterproofing Z Girt and insulation.
We will continue with Plaza concrete, steel demolition, steel replacement, loading dumpsters and receiving deliveries at the East Newton Street gate.
• East Elevation: continue with the exterior window framing, blocking and AVB.
Click here for Two Week Look Ahead Flyer