Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to the weather conditions and existing conditions     found while performing the tasks below. We will be swapping out 30 yd. dumpsters and receiving deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibration and noise, and we are working to minimize the disturbance as much as possible. We will be managing ice melt and snow removal as needed around the perimeter of the site.

 

What to Expect for the Week of January 5th to January 9th, 2026
  • West: No work activities scheduled for this week. 
  • North: No work activities scheduled for this week.
  • East Utility Yard: We are expecting to start the form work and placement of the stair footings. Temporary diesel fire pump being maintained and running for 3 min. approximately every 18 hours.
  • East: We are expected to be out along this side with a boom lift working on metal panel punch list.
  • South Elevation/Plaza: We are scheduling material deliveries throughout the week. We are expecting a crane set up on the edge of the plaza loading material to the activity terrace, Trucks and equipment will be entering through the East Newton St. gate.
What to Expect for the Week of January 12th to January 15th, 2026
  • West: We are expected to start demobilizing the dewatering equipment from this area this week.  
  • North: No work activities scheduled for this area.
  • East Utility Yard: We are expecting to continue with the form work and placement of the stair footings. Temporary diesel fire pump being maintained and running for 3 min. approximately every 18 hours.
  • East: No work activities scheduled for this area, we are expecting to continue working from a boom lift on the metal panel punch list.
  • South Elevation/Plaza: We are scheduling material deliveries throughout the week. We are expecting a crane set up on the edge of the plaza loading material and starting the perforated sign installation. Trucks and equipment will be entering through the East Newton St. gate.

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice