Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible.
What to Expect for the Week of October 21st to October 25th, 2024
• West Elevation Activities: No activities this week
• North Alley Activities: (Albany St. Side) Crane set up and material delivery load large equipment to the 4th floor opening at the NE corner of the building.
• East Utility Yard Activities: Fence install and install electrical equipment and clean up excess material.
• East Elevation: Exterior punch list for the façade.
• South Elevation/Plaza: Curtain wall install, framing, sheathing, waterproofing, Z-Girt, insulation, and metal panels. Start Steel install at the activity terrace. There will be a large Crane at the plaza to remove roofing debris near the end of the week.
What to Expect for the Week of October 28th to November 1st, 2024
• West Elevation Activities: Finish up metal panels over the Sally Port, concrete placements on the interior of the building, trucks will be entering the site from the BMC lot and the gate at the Preston Family building.
• North Alley (Albany St. side) Activities: Load out excess soil, grading, and prep for binder. We are expecting a pump truck set up on the NE corner of the site and placing concrete on the 4th floor.
• East Utility Yard Activities: Grading and continuing with area drains.
• East Elevation: Punch list exterior façade.
• South Elevation/Plaza: Dismantle and relocate mast climbers, framing, sheathing, waterproofing, installation of Z Girt, insulation, curtain wall and metal panel installation.
Click here for Two Week Look Ahead Flyer