Project Photos and Updates

 

Two Week Look Ahead

Please be advised that this schedule may change due to the weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and receiving deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibration and noise, and we are working to minimize the disturbance as much as possible.

What to Expect for the Week of June 8th to June 12th, 2026
  • West: Back fill electrical conduit and subgrade for paving.
  • North: Excavation of the planter material and leak investigation, potentially this week.  We have a crane scheduled for the Valet lot on Tuesday this week, All access down the north alley for residents will be available. A ground crew will provide safe access as needed.
  • East Utility Yard: Temporary diesel fire pump being maintained and running for 3 min. approximately every 18 hours. We are scheduling the new fire pump commissioning this week.
  • East: We are scheduling the window testing along with the roof flooding testing this week along the East Elevation.
  • South Elevation/Plaza: Crews continue working overhead on ACM punch list this week. Several material deliveries are scheduled throughout the week. We expect to start the excavation and installation of the drywell structures this week; trucks and equipment will be entering through the East Newton St. gate.

 

What to Expect for the Week of June 15th to June 19th, 2026
  • West: Delivery and crane truck to install the Sally Port structure this week.    
  • North: We have a crane scheduled for the Valet lot on Wednesday this week, All access down the north alley for residents will be available. A ground crew will provide safe access as needed.
  • East Utility Yard: Temporary diesel fire pump being maintained and running for 3 min. approximately every 18 hours.
  • East: Excavation of light pole bases and site lighting scheduled for this week.
  • South Elevation/Plaza: Crew working overhead on ACM punch list this week along with several material deliveries that are scheduled throughout the week. Trucks and equipment will be entering through the East Newton St. gate. We will be continuing with drilling dowels and plaza deck placement this week.

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice