Project Photos and Updates

 

Two Week Look Ahead

 

Please note that the schedule below may change due to weather, site conditions, or other project needs. During this work, dumpsters may be swapped out, and deliveries may arrive at different times, primarily from the east side of the site along Albany Street. Some activities may cause noise or vibration. The project team will continue to work to limit disruption to residents and neighbors whenever possible.

 

What to Expect: October 19-23, 2026
  • West: Repairs to the existing catch basin, grading, formwork, and concrete sidewalk placement are expected this week.
  • North: Soil disposal may occur this week. Crews are also scheduled to continue formwork and preparations for concrete placement at the accessible ramp.
  • East Utility Yard: Crews are expected to grade and prepare the sidewalk area this week.
  • East Elevation: Crews are expected to excavate for light-pole bases and conduit, grade the sidewalk area, and relocate soil piles for reuse along the east elevation.
  • South Elevation/Plaza: Material deliveries, plaza grading, concrete placement, and curb installation are planned throughout the week. Trucks and equipment are expected to enter through the East Newton Street gate.

 

What to Expect: October 26–30, 2026
  • West: Repairs to the existing catch basin, grading, formwork, and concrete sidewalk placement will continue this week.
  • North: Crews are also expected to continue rebar and formwork activities for the accessible ramp and sidewalks.
  • East Utility Yard: grading and prep for sidewalks and concrete placements.
  • East Elevation: Crews are scheduled to excavate for curb installation, place concrete, and prepare and grade the sidewalk area.
  • South Elevation/Plaza: Material deliveries, plaza grading, and granite curb installation are scheduled throughout the week. Trucks and equipment are expected to enter through the East Newton Street gate.

 

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice