Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible.
What to Expect for the Week of May 12th to May 16th, 2025
• West Elevation: 5/17/25 we will be receiving several truckloads of truss wall material and will be off loading them into the second floor windows from the BMC lot and will continue to load through the windows as needed. We are also expecting a concrete placement this week staged just South of the Sally Port.
• North Elevation: We are expected to have a concrete pump truck set up in the NE corner of the site for a concrete placement through our load dock in the basement.
• East Utility Yard: Temporary Diesel fire pump will be maintained and will run for approx. 3 min. every 18hours.
• East Elevation: Curtain wall install and the completion of the ACM panels.
• South Elevation/Plaza: Steel install, AVB and waterproofing, installation of Z Girt, insulation, curtain wall and metal panel installation. Trucks and equipment will be entering through the East Newton St. gate. Granite veneer install will continue along with plaza slab prep and concrete placements. Daily fuel deliveries.
What to Expect for the Week of May 5th to May 9th, 2025
• West Elevation: We are expecting deliveries, offloading Truss Wall material for H building and hoisting through the 2nd floor windows this week. We are looking to place concrete this week inside the building, trucks and pump will be staged at the South end of the Sally Port and trucks entering from East Newton St.
• North Elevation: No activities planned for this area.
• East Utility Yard: Temporary Diesel fire pump will be maintained and will run for 3 min. approximately every 18hours.
• East Elevation: Curtain wall install and the completion of the ACM panels.
• South Elevation/Plaza: Steel install, AVB and waterproofing, installation of Z Girt, insulation, curtain wall and metal panel installation. Trucks and equipment will be entering through the East Newton St. gate. Granite veneer install will continue along with plaza slab prep and concrete placements. Daily fuel deliveries.
Click here for Two Week Look Ahead Flyer