Project Photos and Updates

 

Two Week Look Ahead

Please note that this schedule may change due to weather or existing site conditions. Throughout the project, dumpsters may be swapped out and deliveries may arrive intermittently, primarily from the east side of the site along Albany Street. Some work may create noise or vibration, and the project team will continue working to minimize disruption to residents and neighbors as much as possible.

What to Expect for the Week of July 20th to July 24th, 2026
  • West: No work is scheduled in this area.
  • North: No work is scheduled in this area.
  • East Utility Yard: No work is scheduled in this area.
  • East Elevation: No work is scheduled in this area.
  • South Elevation/Plaza: Crews are scheduled to replace the deck and complete concrete placement. Excavation and flagpole base installation are also planned. Material deliveries are expected throughout the week.
What to Expect for the Week of July 27th to July 31st, 2026
  • West: No work is scheduled in this area.
  • North: No work is scheduled in this area.
  • East Utility Yard: No work is scheduled in this area.
  • East Elevation: Crews will excavate for light poles and conduit, then continue rough grading and backfilling site utilities.
  • South Elevation/Plaza: Deck replacement and concrete placement are scheduled to continue from the previous week. Material deliveries are expected throughout the week, with trucks and equipment entering through the East Newton Street gate.

Click here for Two Week Look Ahead Flyer 

 

Bus Stop Change Notice

 

The Bus Stop at 88 East Newton Street will be temporarily removed during construction.

The MBTA has decided to direct customers of these four Bus Service lines to two other bus service lines with existing stops in close proximity (less than a block away). See graphic below.

STOP A is E. Newton @ Harrison and will cover the 10 Line (to Copley)

STOP B is Harrison @ E. Newton and will cover the remaining lines 8 (Kenmore), 47 (Central Sq) and CT3 (Beth Israel)

All stops are covered between these 2 locations.

The physical shelter will be removed on June 24th.

The stop relocations will go into effect no sooner than July 11th.

 

The MBTA will issue their own communications to the public on this service interruption.

As a courtesy DCAMM is informing the community early so customers in the area can prepare for this upcoming change.

Click Here for PDF of Notice