Two Week Look Ahead
Please be advised that this schedule may change due to weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and having deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibrations and noise, and we are working to minimize the disturbance as much as possible.
What to Expect for the Week of July 15th to July 19th ,2024
• West Elevation Activities: Metal panel and ACM installation. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate. We are expecting a concrete pump and concrete placement accessing through the gate Preston/BMC gate this week.
• North Alley (Albany St. side) Activities: Fire pump house utilities, backfill and prep for stair pad.
• East Utility Yard Activities: Rebar, form and pour at the utility pads.
• East Elevation: Installation of Z-girt, insulation, metal panels and sloped glazing install.
• South Elevation / Plaza: Framing, sheathing, waterproofing, installation of Z Girt, insulation, and metal panels. Granite installation, plaza concrete, steel install and demolition, steel replacement, loading dumpsters and receiving deliveries at the East Newton Street gate. We are also expecting a crane on the edge of the plaza to remove debris and excess roof material.
What to Expect for the Week of July 22nd to July 26th, 2024
• West Elevation Activities: Continue with Metal Panel installation. Crews will access through the gate near the Preston Family Building and through the East Newton Street gate. We are expecting a concrete pump and concrete placement accessing through the gate Preston/BMC gate this week.
• North Alley (Albany St. side) Activities: form, rebar and pour stair slab at the fire pump.
• East Utility Yard Activities: Continue with forming, prep, pour slabs and separation wall.
• East Elevation: Z Girt insulation, AVB sealants and metal panel and sloped glazing install.
• South Elevation/Plaza: Framing, sheathing, waterproofing, Z-Girt, insulation, and metal panel installation. We will be forming and pouring curbs and slabs around the main entrance. Dumpsters and deliveries will be handled through the East Newton Street gate. We are expecting to start granite installation along the South elevation and steel install.
Click here for Two Week Look Ahead Flyer