Two Week Look Ahead
Please be advised that this schedule may change due to the weather conditions and existing conditions found while performing the tasks below. We will be swapping out 30 yd. dumpsters and receiving deliveries intermittently throughout the duration of the project mainly from the East side of the site along Albany Street. Be advised that all work has levels of vibration and noise, and we are working to minimize the disturbance as much as possible. We will be managing ice melt and snow removal as needed around the perimeter of the site.
The construction site will be closed on December 25th
What to Expect for the Week of December 15th to December 19th, 2025
• West: Continuing this week, we will be hoisting stored material up to the 3rd floor through a loading area which will be done from on site.
• North: No work activities scheduled for this area.
• East Utility Yard: We are expecting to start forming and placing the stair footings and the temporary diesel fire pump being maintained and running for 3 min. approximately every 18 hours.
• East: No work activities scheduled for this area.
• South Elevation/Plaza: We are scheduling material deliveries throughout the week. We are expecting a crane set up on the edge of the plaza loading material to the roof. Trucks and equipment will be entering through the East Newton St. gate.
What to Expect for the Week of December 22nd to December 26th, 2025
• The construction site will be closed on Christmas Day – December 25th
• West: Hoisting of stored material up to the 3rd floor through a loading area which will be done from on site.
• North: No work activities scheduled for this week.
• East Utility Yard: We are expecting to complete the form work and placement of the stair footings. Temporary diesel fire pump being maintained and running for 3 min. approximately every 18 hours.
• East: No work activities scheduled for this area.
• South Elevation/Plaza: We are scheduling material deliveries throughout the week. We are expecting a crane set up on the edge of the plaza loading material to the roof. Trucks and equipment will be entering through the East Newton St. gate.
Click here for Two Week Look Ahead Flyer